German North Sea

Nordseecluster B

RWE (51%) / NBIM (49%)

FID
Schedule
consent / FID
Install window
Foundations 2027 (60 MP); turbines 2028
COD / first power
COD early 2029 (900 MW)
Open vessel demand
What is still unnamed on this farm.

WTG T&I contractor and hull not disclosed for 2028 60x 15 MW

Who to call: RWE Offshore Wind procurement / Van Oord / DEME / Vestas
Packages
Contractor per scope. Blank = not disclosed.
Foundation T&I
Van Oord
Turbine T&I
not disclosed
Array cable
DEME (Living Stone from late 2027)
Export cable
not disclosed
O&M / SOV contractor
not disclosed
Named vessels
2 hulls stamped on this farm.
Living StoneCLV / cableVan Oord foundation spread 2027
Fixtures & open campaigns on this farm
2 lines from the wind fixture book.
DateHullClassStatus
2028unnamed
WTIV / installationOpen — pitch
pitch this month — T&I not named
2027-lateLiving Stone
DEME
CLV / cableIn-house
covered
Source: RWE 27 Mar 2026; Van Oord May 2024 foundations; DEME Oct 2025 IACrwe.comLogged 2026-08-14