SSY Offshore Wind Portal
Wind farms
German North Sea

Nordseecluster A

RWE (51%) / NBIM (49%)

Install
Schedule
install
Install window
44x Vestas 15 MW by end-2026 (Norse Wind)
COD / first power
First power Jul 2026; full COD early 2027
Open vessel demand
What is still unnamed on this farm.

Commissioning SOV/CTV into early 2027

Who to call: RWE Offshore Wind / DEME
Packages
Contractor per scope. Blank = not disclosed.
Foundation T&I
Van Oord (Boreas; 44 MP done 2025)
Turbine T&I
DEME
Array cable
DeepOcean
Export cable
not disclosed
O&M / SOV contractor
not disclosed
Named vessels
1 hulls stamped on this farm.
Fixtures & open campaigns on this farm
1 lines from the wind fixture book.
DateHullClassStatus
2026-06Norse Wind
DEME
WTIV / installationIn-house
covered
Source: RWE 11 Jun 2026; RWE 22 Jul 2026rwe.comLogged 2026-08-14