Nordlicht I

Vattenfall (51%) / BASF (49%)

Install
Schedule
install
Install window
MP/TP from Jul 2026 (DEME); WTG summer 2027 (68x V236-15 MW)
COD / first power
COD 2028 (Vattenfall: cluster operational 2028)
Open vessel demand
What is still unnamed on this farm.

Which DEME/Havfram WTIV for summer 2027; CSOV/SOV for WTG campaign not disclosed

Who to call: Vattenfall BA Wind / DEME / Jan De Nul
Packages
Contractor per scope. Blank = not disclosed.
Foundation T&I
DEME
Turbine T&I
Havfram / DEME (one newbuild WTIV; hull not named)
Array cable
Jan De Nul (Connector; 196 km I+II)
Export cable
not disclosed
O&M / SOV contractor
not disclosed
Named vessels
2 hulls stamped on this farm.
DEME foundation spreadConnectorCLV / cable
Fixtures & open campaigns on this farm
2 lines from the wind fixture book.
DateHullClassStatus
2028-summerunnamed (one Havfram/DEME newbuild)
DEME
WTIV / installationOpen — pitch
pitch — which hull
2027-summerunnamed (one Havfram/DEME newbuild)
DEME
WTIV / installationOpen — pitch
pitch — which hull
Source: OffshoreWIND.biz 4 Aug 2026; Vattenfall/BASF awards; JDN IAC contract; Havfram 2024offshorewind.bizLogged 2026-08-14