UK North Sea (Scotland)
Inch Cape
ESB / Red Rock Renewables
Install
Schedule
install
Install window
54 MP+TP done; 18 jackets + 54 pin piles 2026; IAC from Jul 2026; WTG Q4 2026 ~249 days
COD / first power
First power late 2026; full COD 2027
Open vessel demand
What is still unnamed on this farm.
Which Cadeler M-class (Wind Maker vs Wind Mover) for Q4 2026; jacket/pin-pile vessel unnamed; guard/CTV through 2027
Who to call: Inch Cape marine / Cadeler / N-Sea / ESB
Packages
Contractor per scope. Blank = not disclosed.
Foundation T&I
Jan De Nul Les Alizés (54 MP; done) + Seaway7 Alfa Lift (54 TP; done). Jacket/pin-pile T&I not named
Turbine T&I
Cadeler (one M-class; hull not allocated)
Array cable
N-Sea
Export cable
Enshore Subsea (export lay done; jointing through end-2026)
O&M / SOV contractor
not disclosed
Named vessels
6 hulls stamped on this farm.
Fixtures & open campaigns on this farm
4 lines from the wind fixture book.
| Date | Hull | Class | Charterer / contractor | Window | Status |
|---|---|---|---|---|---|
| 2026-Q4 | unnamed (one Cadeler M-class) Cadeler | WTIV / installation | Cadeler (Inch Cape Offshore) | 72x 15 MW from Q4 2026 ~249 days | Open — pitch pitch — Maker vs Mover |
| 2026-07-31 | Altera N-Sea | CLV / cable | N-Sea | IAC from ~31 Jul 2026 several months | Covered covered |
| 2026-07-17 | Olympic Taurus | SOV | N-Sea (IAC pull-in W2W) | From ~17 Jul 2026 | Covered covered |
| 2026 | unnamed | Foundation spread | not disclosed | 18 jackets + 54 pin piles in 2026 after MP/TP | Open — pitch pitch — jacket spread not named |
Source: inchcapewind.com TP complete Aug 2026; NtM 17/2026; Cadeler 24 Jun 2024; OffshoreWIND.biz 3 Jul 2026inchcapewind.comLogged 2026-08-14