SSY Offshore Wind Portal
Wind farms
UK North Sea

Hornsea 3

Ørsted (Apollo-managed funds co-owner)

Install
Schedule
install
Install window
Foundations Apr 2026–early 2027; turbines from Q3/autumn 2026 into 2027
COD / first power
COD 2027 (2.9 GW / 197 SG 14-236 DD)
Open vessel demand
What is still unnamed on this farm.

Construction SOV/CTV/guard around 197-MP + WTG campaign through 2027

Who to call: Ørsted Hornsea 3 marine / Cadeler / DEME / Seaway7 / Jan De Nul
Packages
Contractor per scope. Blank = not disclosed.
Foundation T&I
Cadeler
Turbine T&I
Havfram / DEME (Havfram 2023 award; DEME acquired Havfram)
Array cable
Seaway7
Export cable
Jan De Nul
O&M / SOV contractor
Esvagt Froude (foundation commissioning SOV)
Fixtures & open campaigns on this farm
6 lines from the wind fixture book.
DateHullClassStatus
2026-Q3Norse Energi
DEME
WTIV / installationIn-house
watch — slot after Windanker
2026-04-24Esvagt Froude
Esvagt
SOVCovered
covered
2026-04-19Wind Orca
Cadeler
WTIV / installationIn-house
covered
2026-04-12Wind Ally
Cadeler
WTIV / installationIn-house
covered
2026-03Isaac Newton
Jan De Nul
CLV / cableIn-house
covered
2022-08-01Unnamed Cadeler F-class
Cadeler
WTIV / installationCovered
Contract subject to Ørsted FID at announcement
Source: Ørsted newsroom; Eastern IFCA NtM Mar–Apr 2026; DEME naming May 2026; Jan De Nul; Seaway7orsted.co.ukLogged 2026-08-14