Empire Wind 1

Equinor

Install
Schedule
install
Install window
54x Vestas 15 MW on Maersk Viridis from 2026 (vessel sailed Mar 2026); Kirby Jones Act feeders
COD / first power
First power late 2026; full COD 2027
Open vessel demand
What is still unnamed on this farm.

Jones Act CTV/guard/barge around first-of-class WTIV campaign

Who to call: Equinor Empire Wind / Maersk Offshore Wind / Kirby
Packages
Contractor per scope. Blank = not disclosed.
Foundation T&I
not disclosed
Turbine T&I
Maersk Offshore Wind (Maersk Viridis) + Kirby Offshore Wind feeders
Array cable
not disclosed
Export cable
Nexans
O&M / SOV contractor
not disclosed
Named vessels
2 hulls stamped on this farm.
Fixtures & open campaigns on this farm
3 lines from the wind fixture book.
DateHullClassStatus
2026-03Maersk Viridis
Maersk Offshore Wind
WTIV / installationCovered
covered — Jones Act feeders Kirby
2022-05-13Unnamed newbuild
Edison Chouest Offshore
SOVCovered
Firm
2022-03-29Unnamed Maersk Supply Service newbuild
Maersk Supply Service
WTIV / installationCovered
Firm
Source: OffshoreWIND.biz 31 Mar 2026; Equinor 2022 charteroffshorewind.bizLogged 2026-08-14