Dogger Bank C

SSE Renewables / Equinor / Vårgrønn

Install
Schedule
install
Install window
IAC Jun–Aug 2026; WTG after B (Voltaire contracted for 87x Haliade-X 14 MW)
COD / first power
COD 2027
Open vessel demand
What is still unnamed on this farm.

WTG hull timing vs DBB overlap; IAC support/guard through Aug 2026

Who to call: SSE / Equinor / DEME / Jan De Nul
Packages
Contractor per scope. Blank = not disclosed.
Foundation T&I
Seaway7 (87 MP complete 2025)
Turbine T&I
Jan De Nul (Voltaire; after A/B)
Array cable
DEME (Viking Neptun)
Export cable
not disclosed
O&M / SOV contractor
Wind Evolution; Norside Cygnus (IAC support SOVs)
Fixtures & open campaigns on this farm
5 lines from the wind fixture book.
DateHullClassStatus
2026-06-21Viking Neptun
DEME
CLV / cableIn-house
covered
2025-02-10IWS Starwalker
IWS Fleet
CSOVCovered
covered — new charter
2025-01IWS Skywalker
IWS Fleet
CSOVCovered
covered — extension
2023-02-09Edda Boreas
Edda Wind
CSOVCovered
covered — commissioning charter
2021-12-09North Star fourth newbuild SOV
North Star
SOVCovered
Firm; approx. GBP90m
Source: Dogger Bank WNoO 20 Jul 2026; DBC IAC NtM 18 Jun 2026; Jan De Nul DBC contractdoggerbank.comLogged 2026-08-14