Dogger Bank B

SSE Renewables / Equinor / Vårgrønn

Install
Schedule
install
Install window
WTG from Feb 2026 to ~Q2 2027 (95x Haliade-X 13 MW)
COD / first power
Full farm COD 2027 (phase B follows A)
Open vessel demand
What is still unnamed on this farm.

Second WTIV already contracted; watch commissioning SOV/CTV through Q2 2027

Who to call: SSE Renewables / Equinor Dogger Bank marine / Jan De Nul / Seaway7
Packages
Contractor per scope. Blank = not disclosed.
Foundation T&I
Seaway7 (foundations substantially complete)
Turbine T&I
Jan De Nul (Voltaire) + Seaway7 (Seaway Ventus from mid-2026)
Array cable
not disclosed
Export cable
not disclosed
O&M / SOV contractor
IWS Skywalker (commissioning SOV)
Fixtures & open campaigns on this farm
4 lines from the wind fixture book.
DateHullClassStatus
2026-02-21Voltaire
Jan De Nul
WTIV / installationIn-house
covered
2025-02-10IWS Starwalker
IWS Fleet
CSOVCovered
covered — new charter
2025-01IWS Skywalker
IWS Fleet
CSOVCovered
covered — extension
2023-02-09Edda Boreas
Edda Wind
CSOVCovered
covered — commissioning charter
Source: Dogger Bank NtM 16 Feb 2026; SSE/Seaway7 contract; OffshoreWIND.biz 9 Jun 2026doggerbank.comLogged 2026-08-14